TITLE: The Performance and Reporting of Expediting Assignments
EQUIPMENT/MATERIALS:
No. Description
1.0 INTRODUCTION
The function of an expeditor is to facilitate the progress of a contract by
taking action as necessary to assist in the timely completion of the work and to
prepare reports in sufficient detail for action to be taken by the purchaser where
the programme of work is in jeopardy.
In order to fulfil these responsibilities the expeditor must be fully
familiar with the requirements of the contract including all the specific
documentation which needs submission and approval as part of the contract.
The purpose of this Work Instruction is to provide guidance to expeditors
on the type of information to be obtained from a supplier and what 'follow up'
action is required if problems or delays are identified.
This Work Instruction is applicable to all expediting assignments for QA
Management Services where clients have not otherwise imposed specific requirements
and for which, specific Work Instructions are prepared.
2.0 INITIAL CONTACT
1. Within 24 hours of receipt of an assignment, the expeditor shall
make contact, by telephone, with the supplier for introductory purposes, on behalf
of QA Management Services and arrange a time to visit the supplier to discuss the
contract.
WORK PROCEDURE
No: WP-15 Rev No: 1 Page: of 7
No. Description
2. During the telephone contact the following information should be
obtained :-
i) Name of regular contact and position within the suppliers
organisation.
ii) Confirm the supplier is in possession of the purchase order
and is able to quote the order number.
iii) Confirm the date of receipt and acceptance of the purchase
order and the acceptance of the supplier to the quoted delivery date.
iv) Enquire the status of drawings and when or if the supplier
intends for drawings to be submitted for Client approvals.
Enquire if drawings are 'for information' (if propriety
items being purchased) or if drawings require 'approval'.
It is important to establish if the supplier does not
intend to proceed unless drawings are approved (when specified).
v) Advise the supplier that in order to effectively expedite
you will need to monitor work against a documented production schedule.
If not already available, attempt to get a commitment from
the supplier that a production schedule will be produced for the work.
(This may not be practical or possible for propriety
equipment being assembled or produced on a production line).
vi) Enquire if any problems exist with the purchase of
materials and identify any critical items of sub-supplied material or equipment
and, if there is, arrange to obtain an unpriced copy of the purchase order for
attachment to the expediting report.
vii) Submit a report on the issues discussed in the preliminary
contact completing all the information required by the attached 'Expediting Report'
form PMP2.08.12F.
WORK PROCEDURE
No: WP-15 Rev No: 1 Page: of 7
No. Description
3.0 REPORTING
Unless advised otherwise, an expediting visit shall be carried out weekly
and it should be remembered that most suppliers will only answer direct questions
and will not normally offer information which has not been requested. It is
therefore important to probe in depth the main points - as listed below - and seek
evidence that what the supplier is saying is factual by sighting drawing registers,
obtaining copies and order numbers of sub-orders etc. and always visiting the shop
floor to ascertain production status.
The following headings must be addressed on each visit :-
Engineering
Drawings
Materials
Manufacture
Sub-contracts
Documentation
Note: It is important that the topics are discussed at every visit even
if, for example, on a previous visit all drawings had been approved. It may be
that modifications have been instigated which result in the revision of drawings.
If this is the case then it will be necessary to expedite approvals through the
system.
(It may become necessary to take action to 'backwards' expedite information
for the supplier from the clients office).
PRELIMINARY
Confirm that all the information in the header of the expediting report are
completed including confirmation of the suppliers understanding of the order basis.
e.g. FOB* - Free on Board
FIS - Free in (Client) Store
EX WKS - Ex Works Despatch
FOT* - Free on Transport
* FOB/FOT should be specific and include location.
WORK PROCEDURE
No: WP-15 Rev No: 1 Page: 4 of 7
No. Description
Enquire from the supplier the expected delivery date which should be the
same as the purchase order delivery date.
The expeditor must now systematically work through the following headings
:-
* Note : If the manufacturer/fabricator is not the party on whom the
order was placed then the information obtained may need to be carried out from more
than one worksite which will require prior approvals before proceeding.
ENGINEERING
Is engineering complete and when specified, have design details been
submitted to the Client for approval or comments?
(Consider if design has, in addition, to be submitted to any
statutory/regulatory authority e.g. Lloyds, DLI, DOHSW, DNV etc).
Monitor status in the event that work will not proceed unless Client
approvals have been received.
At each meeting enquire if any changes to the engineering status exist - a
Client or Supplier may revise requirements part way through a contract.
WORK PROCEDURE
No: WP-15 Rev No: 1 Page: 5 of 7
No. Description
DRAWINGS
Obtain a list of drawings which are being prepared for the work and list
the drawing numbers in the report. Obtain confirmation that, where specified,
drawings have been returned 'approved' by the Client and record the date that
approval was given.
Once all drawings and revisions are approved the list may be dropped from
the report and the word 'complete' inserted.
On each visit the expeditor must enquire of and report any changes to
drawings that have taken place; this is particularly important where design changes
have occurred.
'As built' drawings will often be required as the contract concludes.
MATERIALS
Using the 'bill of materials' or drawings with materials lists, work
through the list and ascertain which items are to be purchased and those to be
drawn from stock.
Enquire if orders have been placed and who are the sub-suppliers.
Obtain copies of sub-orders as evidence that equipment is being purchased
and check delivery dates.
The monitoring of incoming materials is an important part of expediting.
WORK PROCEDURE
No: WP-15 Rev No: 1 Page: of 7
No. Description
If the supplier advises that materials are in the stores then the expeditor
must visit the stores and check that material is available for the work.
During subsequent visits, the outstanding materials list should be reduced
until all items of 'bought in' materials or equipment are in the works.
The contractor should be encouraged to prepare and maintain a "Material
Status Report" even if this is not otherwise specified.
Particularly identify and report on "long lead" items or critical
components.
MANUFACTURE
Manufacturing status should always be assessed by comparison with a
manufacturing schedule or bar chart.
Sufficient breakdown of activities should be made so that progress can be
sensibly monitored.
If slippage to program occurs then the question must be asked how the
supplier intends to recover the lost time. (eg. overtime; extra personnel;
sub-contracting ...)
Where slippages have occurred the supplier must be requested to revise the
production schedule to show how rescheduling will result in finally achieving the
required delivery date.
At all times, constructive advice on how to prevent slippage should be made
and early warnings of delays are essential.
A workshop visit to establish the current status of manufacture is
essential.
WORK PROCEDURE
No: WP-15 Rev No: 1 Page: of 7
No. Description
The objective at all times is to provide an independent report to the
client of the status of the contract.
SUB-CONTRACTS
In a similar manner to the method of expediting from the prime supplier a
similar series of questions is required to be asked of the contractor for all
sub-contracted work or 'bought in' items of plant and equipment which requires sub
assembly or fabrication.
A supplier will often incur delays because of difficulties in obtaining
materials and equipment from a sub-supplier therefore close monitoring of
sub-suppliers is essential.
DOCUMENTATION
The expeditor must list all the documentation which requires submitting as
part of the contract and monitor that submissions are made in a timely manner.
SUMMARY
Summarise the important points of the visit which could result in delays
and include any recommendations or action required by the Client.
The expeditor should always be alert to serious delays, machinery
breakdowns, industrial unrest and financial stability of the supplier and where
slippages have occurred and corrective action not being positively taken by the
nominated contact, the expeditor should seek a meeting with Senior Management to
resolve the matter.
Note : It is a requirement that reports are prepared prior to leaving a
suppliers works and faxed direct to QA Management Services on 09 386 8200 prior to
departing
 |
INSPECTION/EXPEDITING
REPORT |
| CLIENT: |
| PROJECT: |
| CONTRACTOR: |
DATE OF VISIT: |
REPORT No: |
| ORDER DESCRIPTION: |
DATE OF NEXT VISIT: |
ORDER No: |
| ORDER No: |
DELIVERY DATE: |
DELIVERY BASIS: |
| CONTACT: |
TITLE: |
|
| CURRENT DELIVERY STATUS: |
| ADDRESS OF
MANUFACTURER/FABRICATOR: |
STATUS (% COMPLETED)
| ENGINEERING: |
DRAWINGS: |
| MATERIALS: |
SUBCONTRACTORS: |
| FABRICATION: |
INSPECTION & DOCUMENTATION |
|
STATUS REPORT:
|
| SIGNED: |
DATE: |
Page 1 of |